Hi,

what's the use of maintianing production scheduling profile(opkp).

how it'll effect & where.

could you explain in detail about the same.

thanks/regards

vish

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on May 20, 2008 at 07:39 AM

    Hi ,

    Production scheduling profile specifies the automatic actions to be specified while creation and release of a production order , you can maintain the following things in the profile ,

    auto gr , auto release of order up on creation , document updation , capacity and material availablility check etc will takes place automatically according to the selection in the ptofile .

    please let me know further clarification required .

    Regards,

    Mallikharjun.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 20, 2008 at 09:26 AM

    Hi viswanath

    As our earlier peoples input Production scheduling profile does so many things.

    Also in Production order the order type for MTO,MTS,Rework are selected first from this profile only. If it is not there it looks scheduler, Then plant parameter and finally MRP group.

    Regards

    J . Saravan

    Edited by: J. Saravanan on May 20, 2008 11:26 AM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 20, 2008 at 07:42 AM

    Hi,

    Following parameters you set thro Production Scheduling Profile -

    u2022 Automatic actions

    u2022 Release of order on creation

    u2022 Printing of order on release

    u2022 Scheduling of order on release

    u2022 Goods receipt

    u2022 Automatic goods receipt

    u2022 Material availability check

    u2022 Confirm available partial quantity

    u2022 Batch Management

    u2022 Automatic batch creation in the order

    u2022 Batch classification

    u2022 Extend classification

    u2022 Always batch split

    Hope it is helpful.

    Srini

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 20, 2008 at 07:43 AM

    You define the production scheduling profile in OPKP

    & then you assign it to the material master in work scheduling view

    what settings you have maintained in the production scheduling profile will effect when you create production orders

    In a production scheduling profile, you can

    o specify that in a production order or process order particular

    business transactions are carried out in parallel

    - order release on order creation

    - generation of document link from material master on order

    creation

    - generation of document link from BOM on order creation

    - printing on order release

    - scheduling on order release

    - generation of document link from material master on order

    release

    - generation of document link from BOM on order release

    o specify that only partial quantities are to be confirmed in an

    availability check

    o specify that automatic goods receipt should take place

    o enter an overall profile for capacity leveling

    o specify how the capacity requirements of operations should go into

    the basic load

    o specify when finite scheduling is carried out in the capacity

    availability check

    o specify that for the confirmation

    - no deficit quantities are updated

    - no surplus quantities are updated

    - neither deficit nor surplus quantities are updated

    - an adjustment of the operation and component quantities to the

    actual values takes place

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.