hi to all,

i planned costs for a project using networks and activity elements and material components. for the activity elements i placed the costs as a direct input and for material components, i input the required quantity and the material number. However, when i looked at the structure overview(CN41), the materials i placed have 0 cost. YET THE TOTATL AMOUNT in the network&activity INCLUDES the cost of the material (quantity multiplied by material price).

Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Check in OPSV, whether both check boxes are ticked for order type 20 ie network.

Regards

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

CN41 being a structural report will only show aggregated values at activity level. Component values will not be available in this. This is standard system behaviour and not a bug.

You can execute CN52 wherein you can get compenent level prices

Muraleedharan.R

Former Member
0 Kudos

hi again..

i checked both your suggestions but they have already been carried out earlier so the problem lies elswhere..(but at least i was able to eliminate some of the possible causes..).

allow me to give an example of whats happening in my case..

MY INPUTS:

WBS 1

NETWORK 1

ACTIVITY 1

Material Component 1 3 pcs ( 1 $/pc)

Material Component 2 10 pcs (1 $/pc)

Element 1(cost) 500 $

Element 2(cost) 300 $

OUTPUT REPORT:(CN41 - Project cost Sch 000)

WBS 1 $ 813.0000

NETWORK 1 $ 813.0000

ACTIVITY 1 $ 813.0000

Material Component 1 0.0000

Material Component 2 0.0000

Element 1(cost) 500.0000

Element 2(cost) 300.0000

So if you notice in the report the material is 0 but the total includes the material cost..

thanks!

varshal_kachole3
Active Contributor
0 Kudos

hi,

please check the costing variant assignment in OPUV and the valuation variant assigned to this costing variant in Tcode OPL1.the material val tab mention the strategies.

Hope its helpful. rever back if any other issue.

thanks..

varshal_kachole3
Active Contributor
0 Kudos

Hi,

In CJ20n,

Go to the material attached, on the genral data tab, check mark the cost relevent in the top most right corner.

hope it helps.

Reward points if helpful. revert back in any other issue.

thanks..