Routing not getting copied from planned order to production order

Hi PP gurus,

I have created BOM & Routing for Fert material.Both are valid from 19.05.2008.

When am converting planned order to production order today i.e. 20.05.2008 am getting a pop up ''no task list maintained for the material''.

When i check in CA03 & CA02 for the same material , system gives pop up no task list maintained for the material .

In CA01 , for the same material it shows routing is available & asks to create for 2nd counter.

Pls. throw some light on this as am stucked .

Thanx in advance n your solutions will be rewarded.

Regards,

Nagraj Vasmate

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on May 20, 2008 at 06:40 AM

    Hi Nagraj

    You would have created this FERT material Routing in the same group counter of any other material. So while creating it will show the same group counter number of other material.

    Delete the existing FERT routing and recreate the Routing for FERT with different group counter.

    Now you convert from plan order to prod order. Then the system will allow.

    Hope this is clear.

    Regards

    J . Saravan

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      This is in regards with your reply to this thread -

      Hi Nagraj

      You would have created this FERT material Routing in the same group counter of any other material. So while creating it will show the same group counter number of other material.

      Delete the existing FERT routing and recreate the Routing for FERT with different group counter.

      Now you convert from plan order to prod order. Then the system will allow.

      Hope this is clear.

      Regards

      J . Saravan

      I feel in my case it could be the reason why routings are not copied in production order, can you please explain this in details for me?

  • Posted on May 20, 2008 at 06:35 AM

    Hi,

    Check the Routing details in the Table: MAPL, PLKO and PLPO.

    You may get a clue from these tables, why it is not being displayed.

    Regards,

    Siva

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 20, 2008 at 07:07 AM

    Please check the date when the planned order was created . If the planned order was created before 19th or if the BOM explosion took place before 19th the routing will not be copied in the planned order as the routing was created on 19th of May.

    What I suggest here is change the validity start date of the routing to a past date & do the MRP run again with delete & recreate planning data in planning mode & then try to convert the planned order to production order

    I feel it is only the problem of validity date here

    In order to check this try to create a production order with CO01 for todays date & see.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Feby,

      Thanx for ur suggestion ,

      If this is the case , atleast it should reflect in CA02 & CA03.

      as routing was created , i have checked with all validities i.e. in past , present & future dates while CA02 & CA03.

      Pls. revert back.

      Regards ,

      Nagraj

  • author's profile photo Former Member
    Former Member
    Posted on May 20, 2008 at 09:19 AM

    Hi Nagaraj

    Same thing happend to me also at some times. Why i do not know. As you said I will delete and recreate, problem will get solved.

    Regards

    J . Saravan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.