Hi PP gurus,

I have created BOM & Routing for Fert material.Both are valid from 19.05.2008.

When am converting planned order to production order today i.e. 20.05.2008 am getting a pop up ''no task list maintained for the material''.

When i check in CA03 & CA02 for the same material , system gives pop up no task list maintained for the material .

In CA01 , for the same material it shows routing is available & asks to create for 2nd counter.

Pls. throw some light on this as am stucked .

Thanx in advance n your solutions will be rewarded.

Regards,

Nagraj Vasmate