HI Gurus,
We are manufacturing LCD TV & having REM.
We are created BOM for LCD TV includes assy LCD PANEL MATRIX.This assy LCD PANEL MATRIX is made up of LCD Panel & several other items.
This LCD Panel is procured from different vendors e.g.LG ,SAMSUNG,SHARP etc.. with different code.
Now ASSY LCD PANEL MATRIX BOM is made with one of the panel code.
Finally LCD TV BOM is made with this ASSY LCD PANEL MATRIX & several other items.
Now my problem is how to include other vendor Panel in BOM.(I do not want to use alt.BOM).
kindly suggest....
rg
Tushar
kindly suggest
rg
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Can we use revision level & change no. to include the other lcd panel with single BOM for assy lcd panel matrix & maintaining this assy code in main BOM.
rg
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you have a predefined Usage probability , you can go for Alternative BOM Items , by defining the LCD panels fron various vendors as alternative items
Alternative Item is an item used as an alternative to one or more BOM items.MRP plans alternative material components according to usage probability.
Alternative items are selected automatically according to:
Priority
Strategy
Usage probability
Regards,
Sheik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
One clarification required..
How and on what basis you decide which LCD Panel to include?
Regards,
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.