MODERATOR: All points have been UNASSIGNED and the thread LOCKED. Please do not share email addresses, documents, or links to copyrighted or company confidential information on these forums. If you have some information, please consider posting it to the [Wiki|https://wiki.sdn.sap.com/wiki/display/ERPFI/Home] rather than sharing via email. Thank you for your assistance.

Hi all,

plz tell up integration points of PS-PM for carrying out maintenance project? in detail plz...

regards

pushpa

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

The integration between PS and PM is needed when we need a Major maintainance activity to be monitored minutely (imean when you need a separate planning, Budjeting and execution) As mentioned by other PM order can be assigned to WBS for exectuion phase of the project.

Please let me know if you need any specific details

Thanks

Former Member
0 Kudos

Hi,

Can you please tell the SPRO setting for this regarding PM PS integration.

How will the PM activities be mapped in PS as both of them can be linked by relationships.

Former Member
0 Kudos

hi shourya,

plz help out with PS-PM scenarios as my new project assignment is on tht , any doc plz send the same to

kollapushpa[at the rate]yahoo[dot]com

regards

pushpa

Former Member
0 Kudos

Hi

You use the entries in the PM/PS reference element to populate the corresponding fields in task lists and maintenance plans in Plant Maintenance, and WBS elements and network activities in the Project System.

By maintaining the same entry in different areas, the system copies the values to the PM/CS orders when they are generated, and you can use these values for automatic assignment from PM/CS orders to projects.

regards

Shourya

Former Member
0 Kudos

Hi,

You can assign PM order to WBS or Network activity on additional data tab of order. What this will do is that the al the postings made on the PM order will be booked on WBS/Network and we can also use budgeting via linking WBS/Network to PM order.

Regards

Jatinder Bansal

Former Member
0 Kudos

Hi,

You can assign PM order to WBS or Network activity on additional data tab of order.

Regards