WIP balance transfer to subsequent production order, is this possible.

Jan 23 at 02:31 PM

20

avatar image
Former Member

We are from a diaper factory were the machines are not stable enough to consume all the raw material ordered per single day. There is always a remaining quantity of each raw material at the end of each day of production. In the fresh work order the SAP system calculates the needed raw material on the basis of the bill of materials. Hence, new set of raw material is transferred from the raw material warehouse to the production warehouse both in the SAP system and physically, in addition to the WIP of the previous day.

Therefore I am looking for a clarification in which to put the WIP balance of each items back to the system so that it can calculate the change in demand and ask the raw materials warehouse waht is the balance instead of fresh request on the basis of the bill of materials.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

0 Answers