Hi

I want to copy materila from one plant to another plant in MM01 i can copy material one by one , but if i have to copy bulk of material how to copy that.

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • Posted on May 19, 2008 at 09:12 AM

    Hi,

    No standard SAP transaction exist for this purpose. Please try to use LSMW.

    BR

    Csaba

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 19, 2008 at 09:12 AM

    Hi

    U can use LSMW to mass Upload of material to new plant

    Vishal...

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 19, 2008 at 09:13 AM

    LSMW

    http://www.sap123.com/showthread.php?t=98

    Go through the link...

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 19, 2008 at 09:16 AM

    Hi,

    To copy the material from one organ units to another,Use LSMW with t.code:MMZ1, you can use BDC also.

    Regards,

    Biju K

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 19, 2008 at 09:27 AM

    Dear

    you can try LSMW or BDC with your ABAPER help.

    Regards

    venu gopal

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 19, 2008 at 09:36 AM

    dear avi

    you can do this by mass maintains of material master..

    follow the steps:

    1.) go to se 16 enter the MARC table and enter ur plant in which ur material exist .

    2.) now export that list of material to exal sheet ..( go to system > list > save--> local file than spread sheet )

    3.) now go to MM17

    select Plant Data for Material (MARC ) table and execute ..

    4.) go to data record to be create tab .

    5.) now click on multiple selection button . and enter your all material list . ( just copy from excel sheet and click on a button having icon like save button in multiple selection screen , name is " copy from clipboard " ) all material number will be copied to .

    6.) enter plant in which u want to extend ( you can enter more than one plant also using multiple selection option )

    7.) now for reference just enter plant number in source and execute ..

    8.) new material will be created at new plants by copying all the data from old plant ..now to make changes in any field of material master u can run mass changes

    hope this will solve ur problem

    Reward points if helpful

    Thanks and regards

    Ravikant Dewangan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.