Hi Team,

I am working on subcontracting Process from refurbishment Order

i have checked Subcontracting checkBox for PM02 Key and triggered PR and from PR

PO and GR Done but while confirming operation from IW41 Getting ABAP Dump

Getting messager

A raise statement in Program "SAPLCOBO" has raised exception condition "Not Found"

please help

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Mar 14 at 12:31 PM

    Issue Solved with SAP Note: 2416822

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 23 at 08:33 PM

    See if SAP Note: 1731736 has been implemented, if you are on EhP 5 or 6.

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Tom,

      This note is for those who has operation account assignment, but we have not implemented Operation account assignment

      we dont have operation costs

  • Jan 24 at 04:56 AM

    Hi Ashok,

    Can you share the Abap dump screenshot ?

    Regards

    Terence