Hi All,
I have a scenario as follow :-
<u>Material A</u>
<b>Safety Stock :</b> 200
<b>PIR for Month 1 :</b> 150
<b>Current Stock : </b> 220
Using Make to Stock Strategy 40, when I run MRP, it will create a planned order for Material A with the quantity of <b>130</b> for Month 1.
Is there any strategy that I can use to force MRP run to create a planned order for the full quantity of PIR, which is <b>150</b>?
Thanks