Hi all,

how would it be possible to add a additional production task to an already released production order? Or, at least, to an additional operation to an existing production task?

Is that possible at all?

Kind regards

Klaus

Accepted Solutions (1)

Accepted Solutions (1)

former_member251576
Participant

Dear Klaus,

Currently it is not possible either to add an additional production task to a production order which is released or to add an operation to an existing production task. Production totally depends on Master Data. Here everything has to flow from Master Data first.

Regards,
Kopal Upadhyay

Answers (1)

Answers (1)

Klaus01
Participant
0 Kudos

This is really unflexible 😞