Dear All,
I am new in the scenario of scheduling aggrement.Pls help me in solving my query:
I have created a SA thru ME31L with type as LP with validity from 16.5.2008 to 16.10.2008 for 30 pcs.
Then I have created delivery schedule thru ME38 as follows:
16.7.2008---10 pcs
16.8.2008---10 pcs
16.9.2008---10 pcs
I dont have release strategy so no question of release.
1) When I am going to do GR with respect to this SA with document and posting date as 16.7.2008, system is giving a message Document xxxxxxxxxxxx doesnt contain any selectable items. Why????
2) Do I have to maintain any PO in between SA and GR?
3) If yes, then what is the use of creating delivery schedule?
Regards,
Indranil