Skip to Content

How to do GR differently for raw material and packaging material?

Hello Guys,

I want to do GR differently for raw material and packing material. Example-I have created a PO 100kg when material reached i want to do GR for raw material as 95Kg and 5kg as packing material how to to map in sap please suggest.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jan 22 at 07:09 AM

    Why don't you order it this way? How should SAP know that 5 kg of the ordered quantity is packaging? And what can you do at all with the used package if the product is still in?

    Add comment
    10|10000 characters needed characters exceeded

    • Jürgen L Amiya Ranjan Behura

      This process requires much more input from your side, as it is not at all how other companies work. 2 and half line is certainly to less input.

      What do you order? just the rice of the packaging as well?

      What do you want to put into inventory? Just the rice or the packaging as well?

      for what is the price? for what do you pay your vendor? just for the rice of for the packaging as well?

  • Jan 22 at 09:47 AM

    From your input, i think you should separate two materials: 1 is rice the other is packaging material, then in PO you order two items. let's say

    normally you receive 95kg of rice and 5kg of bags-> you may order just like that and maintain some delivery tolerance for each item in the PO or even in material master data then when goods arrive, you do GR and adjust as the correct quantity for each.

    i think that is the easiest way to track your inventory.

    Add comment