Hi Experts,
I have a problem in CK40N, not sure whether its my understanding wrong or is it the way SAP Works,
I am costing a material in CK40N, which is extended to two plants, in one of the plant A there is already a cost estimate and in another plant i dont have the cost estimate at all.
In selection crieteria of CK40N, i just give the materials alone and not the plant and i enable "Always recost material", currently what it does is its costing both the materials. Logically since ive enabled "Always recost material", it should recost only those parts which have already a released cost estimate, but it costs both the materials which as cost estimate and another which doesnt have an cost estimate.
Plant B material is an STO and we cost them separetely with reference to plant A.
My understand is always recost material means it will recost only those materials which as released cost estimate.
Can anybody clear my clarification
Thanks in advance
Best Regards
gj