Hi All PP guru
I found out that even there is no goods issue to production order, when i run CLSD the prd order still can be closed . Is this the standard process ?
Can we schedule CLSD as background job ? If we schedule as background job, then it would be tesdious, as we need to select the prd order that is DLV status and TECO status.
Regards
kn