Hi everyone,

I'm looking to know how to create a substitution rule so an fields in the proj is copy in PRPS.

Change we did was to put media code as dual (so you can enter information in both level, Project or WBS) I'm able to copy the media code to the WBS but the submedia code is not working. This is the substitution rule that I create .

prerequesite:

PROJ-ZZLOWER8 <> 'X'

and

substitute:

media code field PROJ-ZZMEDIA

Submedia code field PROJ-ZZSUBME

when the box is empty (with no X) then information at the project need to be copy to the WBS level but it's not for the Submedia code. Just so you know it's not all media code that have a submedia code.

Can someone help me with this?

Thanks

Marianne

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Maria Terence Jan 25 at 07:55 AM
0

Hi Marianne,

What is the Sub-Media Code is another field value which needs to be copied ? Try to create another substitution rule for Sub_media code to copy based on the Media code is available or not.

Also check with your abaper whether any partial code can be entered to do the same.

Regards

Terence