on 05-14-2008 7:20 AM
Dear All,
I have to use period end activities in my project for that i need some information about Result Analysis.and
I also request to send me Configuration Document of RA .....
Regards
Lallan.
Check out this link...
http://help.sap.com/bp_iasifrsv1470/BBlibrary/Documentation/I58_BB_ConfigGuide_EN_DE.doc
Reward points if helpful.
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In short please follow these steps:
1. Maintain RA Key (Tcode :OKG1)
2. Maintain RA Version (Tcode :OKG2)
3. Define Valuation method for RA (Tcode : OKG3)
4. Define Line ID's
5. Define Assignment of RA (Tcode :OKG5)
6. Define Update for RA (Tcode : OKG4)
7 Define Posting rules for settlement to accounting (Tcode: OKG8)
8. Maintain the RA Key in Tcode: OPSA Controlling tab, if the Defualt RA key is to be maintained while creation of the project.
Beside this please follow the link below:
http://help.sap.com/saphelp_46c/helpdata/en/3d/72369adc56d11195100060b03c6b76/frameset.htm
Hope its useful.
Reward points if useful.
thanks..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.