How do we use Simulation ?

Dear Experts,

Please tell me about the use of simulation. what are the requiremnets to use Simulation and how can we see the effects of it at user level..??

Thanks in advance..

Regards

Lallan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    May 14, 2008 at 06:29 AM

    Hi

    When you are planning complex projects, for instance in engineering-to-order, it is often necessary to simulate and save changes to a project, without affecting the operative project. To do so, you use simulation versions that can be changed, costed and scheduled unlike project version.