Hello Gurus,
I have created the process order for HALB (Semi Finished Goods) material. For the same material standard cost estimates has been run and all the cost have been captured properly.
While i m running the overhead calculation for process order via T Code KGI2. I am not getting the actual overheads.
I have checked all the configuration regarding costing sheet, calculation base and credits. I found alll these correct.
and the noted point is that i m getting the actual overhead for another process order for the same material. I have checked Production Versions, Material Recipe and BOM. All these i found correct.
Please be needful to me in this regard. its very urgent!!
Regards,
Jigar