Dear experts,
I have below scenario regarding PP-WM interface,
1.Production order create for material which has production scheduling profile, and profile has been designed to create transfer order when production order is released.
2. all components in the production order had stock more than required quantity when order was released.
3. all components in production order are maintained with WM view in material master.
4. components are assigned to an operation which is performed at a work center assigned with production supply area.
with all above conditions , is it possible that system does not creates a tarnsfer order when production order is released but generates a transfer requirement.
your reply will be greatly appreciated and will surely be rewarded.
Thank you
Anand