Use BOM in Project System

29 Views

I have a construction project (IDES) include an activity is “0001 build 5m2 wall”,

WALL (1m2) = CEMENT(100 kg) + BRICK (100 pies) + SAND (700kg)

My idea is make a semi-material named WALL, unit m2 with BOM as above norm

And then I will assign 5 WALL to the activity 0001, require date 14/05 to when MRP run it generate requirement of CEMENT, BRICK and SAND with required date is 14/05 too

My questions are:

Is my idea possible?

How about some mater data for WALL such as: MType, Price control, MRP type, Procurement type, In-house production, Plan delivery time,..?

or do you have any other solution?

Thank you