Hi

We would like to upgrade our ECC system from ECC 6.4 to S/4 HANA. What will be the impact to connected BW system which is BW 7.5 on oracle DB?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jan 22 at 10:03 AM

    Hi AMS,

    Migration to S/4 HANA is done one by one. It is never expected to migrate all the system at a time. This way you should be able to run BW on oracle DB along with S/4 HANA system.

    I had been part of one BW migration to HANA and it was connected to ECC6, EhP6 (Oracle DB) and it has been working. Your scenario will also work.

    @Moderator: Pease correct me if I am wrong.

    Regards

    Shakeel

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 30 at 09:26 AM

    I think more important is the question which extractors will work after the S/4 migration.

    Please check notes:

    2500202

    2289424

    Regards,

    Torsten

    Add comment