Hi Experts:
Taking into account the following scenario:
Task based MLC
Cost rate A defined
- From 2007.01.01 to 2008.01.01 of 100 /h;
- From 2008.01.02 to 2009.01.01 of 110 /h;
Task, with a resource assigned from 2007.12.01 to 2008.02.01 and workload of 50 h. The resource has the cost rate A assigned.
Which will be the final budget for the task? Does the ECP take a different line for each rate?
Kind regards,
Neil