CJ20N - Network Activity - Maximum number of splits (254) reached

Jan 17 at 03:38 PM

48

avatar image
Former Member

Hello colleagues,

Could you help me? I am trying to figure out if there is a way to increase the split number more than 254. I need assign more than 500 people at person assignment tab in the network activity, cj20n transaction.

Thanks a lot,

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Maria Terence Jan 25 at 07:59 AM
0

Hi Vanessa,

I dont think you can. But raised a OSS note to SAP or check for notes

Additionally, you can split the activity into 2 or more based on certain group of users, which can make your life easier.

Regards

Terence

Show 2 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi Terence

Thank you for your answer!

That´s exactly what we are doing now. We´ve splited into 2 ou more activities. But the client wants to use only one activity.

Regards

0

Hi Vanessa,

Try to convince the client, if that's not possible then raise a OSS note to SAP and get an update.

SAP can provide a work around.

Regards

Terence