Hi Experts,

I have created a Inbound delivery in ECC but it got saved with error message -"shipping notification could not be distributed"

Then i have checked application log with tcode SLG1

then I found below error.

Warehouse DAD: no workload times maintained for process Goods receipt / putaway

Please help me in this.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Jan 17 at 02:19 PM

    It would be good if you could add the message class and message number to the message text "Warehouse DAD: no workload times maintained for process Goods receipt / putaway"

    Usually Google knows already all SAP message, but this message is unique in a Google search.

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 17 at 02:10 PM

    Hi Dhilip,

    Please check if at the po item level confirmation tab-confirmation control key is selected as 0004(Inbound delivery),

    if yes pls update

    Regards,

    Anese khan

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Anese khan,

      May i know the exact configuration required for confirmation control key to distribute the inbound delivery to EWM or any other external system.

      Regards,

      Dhilip

  • avatar image
    Former Member
    Jan 19 at 11:02 AM

    Hi Anese khan,

    May i know the exact configuration required for confirmation control key to distribute the inbound delivery to EWM or any other external system.

    Regards,

    Dhilip

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 19 at 11:52 AM

    Better focus on the message.

    There is usually a kind of a logical hierarchy among the messages in a log, means you have messages on the detail of an action and a kind of a summary. You have the message "Warehouse DAD: no workload times maintained..." and because this is an error the overall goal of posting the Idoc could not be achieved and because of this you get informed about this via the error: "shipping notification could not be distributed"

    The inbound delivery already exists, so I would not expect that the confirmation control key is wrong.

    You have not answered yet my question for the error message number.

    You also had not commented on the fact whether you have workload time maintained somewhere.

    Add comment