on 01-17-2018 4:29 PM
I'm using MD61 to create an individual requirement for a material but it wont allow me.
I don't think the MRP views are set up to allow me to do so,
can someone help as to what they should be.
Thanks
Hi,
If Strategy Grp not maintained in the Material master level, Try to check "User Parameters" tab in MD61 screen and maintain the requirement type. Then system will allow you to create PIR.
If you need further details, please post your Error Screenshot for better understanding of your Qns.
Best Regards,
Kumar Semmalai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Plz maintain strategy group 40 or 10 in Material Master -MRP3 View.Check and Revert.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Plz maintain strategy group 40 or 10 in Material Master -MRP3 View.Check and Revert.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Jacqueline
Your question is not exactly clear for me. What do you mean by creating an individual requirement in MD61? Which strategy are you trying to use and what is exactly your business scenario? What do you mean when you say that the MRP views do not allow you to do so?
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.