Appropriation request - Investment management. (configuration)

Hi All,

I am going to implement appropriation request and Investment management.

1st. What kind of configuration required?

2nd. How can we activate the workflow for the appropriation request ?

3rd. Can we linked the appropriation request to IM module ? in another word, let say we have put some amount in appropriation request, then can we make it automatically allocated in IM module

4th. Please advice.

Cheers,

Nies

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    May 13, 2008 at 02:26 PM
    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 14, 2008 at 03:47 AM

    Regarding Appropriation Request Configuration:

    1. Maintain Appropriation Request Types

    2. Define Number Assignment

    3. Define Screen Layout for Appropriation Requests

    4. Define User Statau

    5. Assign User Status to Approp. Request T

    For Cost Planning:

    6. Define Costing Variants

    7. Define Planning Profiles for Cost Planning

    8. Assign Approp. Request Type to Planning

    Hope this helps.

    Venkat

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 12, 2008 at 09:11 AM

    Refer the response to similar post.

    appropriation-requests

    The configuration and the workflow settings are mentioned to extent possible.

    Regards

    Sreenivas