Dear PM Gurus,

My question is in relation to PM Order Confirmations (time confirmations) by IW41. In this menu there are two check boxes with the names

Final Confirmation

No Remaining Work

Can any one explain me the difference between these two? One thing I know is if I tick Final Confirmation and save, the system won't allow me to enter times entries for the particular operation again. But if I don't tick Final Confirmation but tick No Remaining Work and save, the system still allows me to enter times for the particular operation afterwards. (until Final Confirmation is ticked)