Hi all,
I need to get a table or FM through which i can findout the remaining workcenter capacity(work) assigned with the network order for each period. In RPSQT table i can get only planned capacity.
The transaction for the same is CM07 and in the settings we have planned or remaining option.
I need to findout from where the remaining capacity data is coming into CM07 transaction.