Hello Experts,

We have a requirement not to call the maintenance plans while our equipment in storage. Is there a way to push out the maintenance plan's, plan date till tomorrow if Ip10/ IP30 runs today?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Peter Atkin Jan 17 at 08:22 AM
0

Or make the plan inactive in transaction IP10/IP02 via menu path: Maintenance Plan->Functions

PeteA

Share
10 |10000 characters needed characters left characters exceeded
RAKESH MANE Jan 17 at 05:15 AM
0

Hello

You may use the skip Call option in Ip10.