Is there a way to pushout the plant date of a maitnenace plan

Hello Experts,

We have a requirement not to call the maintenance plans while our equipment in storage. Is there a way to push out the maintenance plan's, plan date till tomorrow if Ip10/ IP30 runs today?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jan 17 at 08:22 AM

    Or make the plan inactive in transaction IP10/IP02 via menu path: Maintenance Plan->Functions

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 17 at 05:15 AM

    Hello

    You may use the skip Call option in Ip10.