new planning strategy

17 Views

Dear All,

i want to create new planning strategy for the below said requirement,please tll me how to create the new planning strategy ,

do not want to consider the previous month production order qty and plenned order qty (Nothing but WIP qty) in the current momth MRP, but the stock has to consider in MRP.

Example,

Before MRP,

material : XYZ

Stock : 1000

Prod Qty : 500 for 02.04.2008

PIR Qty : 2000 for 02.05.2008

After MRP, the requirement should be as below said,

material : XYZ

Stock : 1000

Prod Qty : 500 for 02.04.2008

PIR Qty : 2000 for 02.05.2008

Pld OrdQty : 1000 for 02.05.2008

For the above requirement ,i have done settings in the availabilty check like , for include planned order and include production order are "DO NOT TAKE IN ACCOUNT".

Even then also the planned order qty is generating for the "500" only.

Thanx in advance.

Regards

Srinivas