Dear All,
i want to create new planning strategy for the below said requirement,please tll me how to create the new planning strategy ,
do not want to consider the previous month production order qty and plenned order qty (Nothing but WIP qty) in the current momth MRP, but the stock has to consider in MRP.
Example,
Before MRP,
material : XYZ
Stock : 1000
Prod Qty : 500 for 02.04.2008
PIR Qty : 2000 for 02.05.2008
After MRP, the requirement should be as below said,
material : XYZ
Stock : 1000
Prod Qty : 500 for 02.04.2008
PIR Qty : 2000 for 02.05.2008
Pld OrdQty : 1000 for 02.05.2008
For the above requirement ,i have done settings in the availabilty check like , for include planned order and include production order are "DO NOT TAKE IN ACCOUNT".
Even then also the planned order qty is generating for the "500" only.
Thanx in advance.
Regards
Srinivas