Dear Friends,
Please suggest me for the below scenario...
My work center start time and end times are (6AM - 10PM). It will work only A & B shifts. On this work center I am doing a kind of Heat treatment (Induction hardening). Generally this operation may take 3 to 5 hrs of time. But partial confirmation of this operation is not possible. Hence if the remaining available capacity on the work center is sufficiant for a given day... then only it should be scheduled on that day. This I am going to do through capacity leveling (CM25).
If any further clarification is required... please let me know.
Regards.