Planning run

Former Member
0 Kudos

Dear all

where can we use transaction code MDBT

How to run mrp for a plant ( spares) for which CBP is set

Reorder point is fixed

Please give differences between manufacturing plant planning run ( MRP type is PD) and spares plant( MRP type is VB)

Accepted Solutions (1)

Accepted Solutions (1)

former_member335796
Active Contributor
0 Kudos

Hi,

You can not execute planning run specifically for Materials with VB.

But, If you run MRP for higher level materials (MD01/MDBT or MD02) being the lower level Materials they will be included in the Planning Run.

How the system will know that the Stock is blow the Reoprder Level?

Unlike the Materials with PD, for the VB Materials, when the Sock is below the Reorder Level then the Planning File entry will be set for these Materials.

So, afterwards when ever there is a planning run, system will consider these Materials in the Planning Run.

Appropriate Procurement Proposals will be generated for these Materials.

Hope this clarifies..

Regards,

Siva

Answers (2)

Answers (2)

Former Member
0 Kudos

thanks

Former Member
0 Kudos

Hi,

1.where can we use transaction code MDBT?

MDBT is for running MRP in the background

2.How to run mrp for a plant ( spares) for which CBP is set?

MD01 is the safe bet

3.Please give differences between manufacturing plant planning run ( MRP type is PD) and spares plant( MRP type is VB)

In case of first plan you can run for a particular finished product in MD02

Where as for VB you cannot run for a specific material as the system need to check all the raw material for which you have Set MRP as VB & moreover its not based on any particular requirement & as it is based on the stock level & re order point

Hope the above is useful

Regards,

SVP