Skip to Content
0
Former Member
May 09, 2008 at 10:38 AM

Valuation problem for materials ex project

48 Views

Dear experts,

My client needs to return remaining materials from ex project to the unrestricted stock in the inventory management. Those materials was bought thru expense (non-stock) purchasing assigned to the WBS element (account assignment P).

My questions are:

1. Is it possible to record the ex-project materials as non-valuated in the inventory management?

If it is, how to post those materials to the system as non-valuated?

2. If we want to record the ex-project materials as valuated stock:

a. Which value that will be used by the system as the material valuation?

Is it from the value (Moving Average / Standard Price) maintained in the material master record

(accounting view)?

b. Can we input another value (thru MIGO transaction) as the material valuation?

Please advise.

Thanks before.

Regards,

Rumata