Skip to Content

Settlement of Actual Cost from WBS to Service Order

Dear All,

I would like to settle the Project WBS Cost to Service Order. I have maintained settlement rule in WBS as CAT :ORD and Settlement Receiver : CS Order number, But, when I am running settlement in CJ88, it's not settling any values, even though there is debit on the project (for Secondary + Primary cost).

Kindly advise me if am missing with somehting.

Regards

Atul Rajmane

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 18 at 11:04 AM

    Hi Atul,

    Actually what is the error message you are getting.

    Did the value of the Service is increased by the amount you settled from WBS ?

    Regards

    Terence

    Add comment