Skip to Content
0
Former Member
May 09, 2008 at 08:50 AM

system ignoring the Public holiday while providing GI date in sales order.

286 Views

Orders being raised against plant UK appear to be ignoring the fact the 5th May is a public holiday in the UK and are dating incorrectly.

Problem Description

When orders are being raised against sales organization GBA with delivery from plant UK, the dating process appears to be ignoring the fact that the 5th May is a public holiday.

Screen shot below shows the actual dates that were calculated.

I am getting the same problem if I try and enter a new order today. The system is calculating that we are able to deliver these orders on 6th May, which based on the lead time from plant UK the earliest date we should now be able to deliver is 7th May (taking into account weekends and the public holiday).

Can you advise on why the system is dating incorrectly please.