Hi

I have create two activities(one internal and other External) under one WBS Element.

I have complete the process of confirmation(for Internal activity) and Purchase process for external activity.

Now i can see both the planned and actual costs of those activities.

Now i want the see the costs at WBS Level, which is now happening.

pl guide me, where i can see and what will be the process.

Thanks & regards