Hi,
I have setup classic Kanban for a raw material. I have setup the control cycel for external procurement thru scheduling agreement. The system now shows the kanban bins in "wait" status. I run the Kanban signal and the status changes to "empty" and generates the Schedule Line. I compelte the GR and the status changes to "Full". Now this material is consumed thru production or issued to a cost center. The status of kanban does not change to "empty" again. I have to manually change the status. Is there any way by which this issue can automatically change the Kanban status?
Thanks