Hi,
I hope you are doing well. I have imported the ATP customizing from ECC to APO.
For deliveries the check instruction imported for chkmode=046 and BEvnt=BE combination states that the Product Check option is to be used.
In trx Maintain Check Control (under Global ATP
>Product Availability Check
> Maintain Check Control) I have the combination 02 BE.
I'm using a make to order scenario.
The problem comes because when I try to create a delivery for Plant C010 I have the quantity proposed automatically and the lot selection works fine.
But for plant MQ01 the system does not propose any quantity and creates a log that says that there 0 quantity available for that order.
The MRP data in material master data in ECC is the same for both plants. What else can I check?
Best regards and thanks in advance
-Italo