Changing 'Z' movement type for old orders

0 Kudos

Hi All,

My client has requirement for changing it's movement type as they were using 'Z' movement type instead of standard movement type '261' on specific order type. Now it has been replace with standard movement type by committing ABAP code but old order still showing movement type 'Z' instead of standard '261' so is it possible to change movement type for old maintenance order as I can't find anything on forum.

Regards,

Faizan

Accepted Solutions (1)

Accepted Solutions (1)

peter_atkin
Active Contributor
0 Kudos

Faizan

Try deleting the relevant material rows in the PM/CS order and save.

Then re-enter the order and add the materials again.

PeteA

Answers (1)

Answers (1)

0 Kudos

Peter,

Thanks for your reply, I think this is the only solution.

Regards,

Faizan