Hi All,
I am working on BI Integrated Planning (formerly BPS) project. In my design:
1. Sales quantities plan in BI will be used as a basis for the production quantity plan.
2. This will then be retracted from BI to COPA.
3. A program will be used to copy production BOMs & Routings to costing BOMs & Routings
4. Then Update new Costing BOMs and Routings using mass update functionality (transaction codes CS20, CA85N)
5. Then use another program to explode BOMs and Routings to arrive at Activity Plan.
Can anyone share a program that does 3 and 5 above.
Thanks in advance,