Hi Experts,

I have been using the Edit > Component Availability ATP (Shift + F7) function to check component availability on planned orders through MD12. Usually I just get a list of components colour coded to indicate whether or not I have missing parts. For one particular material though the check is bringing up a "Confirmation Proposal" screen

The ATP quantities button takes me to CO09. The component material is very busy with lots of order reservations, dependent requirements and independent requirements, so it is difficult to read availability from CO09, but I want to know what it the trigger for showing this screen over a simplified Yes / No availability list.

Thanks

Jez

b3gio.png (22.1 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Jez Lawson Jan 25 at 08:05 AM
0

I found the answer. If there is a single material in the BOM this screen displays. The information required shows in the confirmed quantity. Its not as immediately clear as the colour coded screen, but all the info you need is there.