Hi Experts
Now we met one problem. mrp runs out the plan order-> pr->po. but In PO, the delivery date is different from the date in PR. like PR delivery date is May 28 , but in PO, the delivery date is May 14.
We are confused why it changed and which impact this date calcualtion?
Thanks