I have a problem with EDI 945, 945 is WMS transaction type which happens in VL02n for processing PO and STO.
Procedure includes for automatic and manual PO,
1. Create a PO (NB type) then
2. Create a STO putting PO in reference field.
3. Run a customised programme for EDI 945.
4. Add materials through processing flatfiles.
5. line item is added to STO
6. EDI programme includes creating delivery, shipment, PGI for materials.
7. Idoc produced automatically for Delivery
Problem: when materials added in programme step 4, date for line items have to change as per STO created date instead of that its showing date of materials processed.
Note: Change applicable if there is ATP set .
Please suggest how to solve this problem.
Thank you,
Raj
Edited by: Kalyan raj on May 7, 2008 5:29 PM