Gurus,
We have established release strategy however our clinet wants that after the PO is released and changes after release such as adding line item should re trigger the release of PO though the total value of the PO may not exceed the approval limit that has already been done. For example a PO has $ 300,000 and it is released by a code/group whose limit is $999,999.
Once the order is released, the line item added with a value of $200,000. Now after the line item added, the total value does not exceed the limit $999,999 but clinet wants that PO should be subject to release by the approver. could any one suggest a meaningful solution.?
Cheers