Dear SAP Experts,Please share your inputs to resolve below query.

1. We have one STO created from Plant A to Plant B for 3000 Units.(Both Plants under same company code).

2. Partial GR has been done for this STO already for 2000 Units in SAP.

3. The Further Stock of 1000 Units was in TRANSIT but was cancelled in VL09 later on by us.

4. The PO order history shows the GR document for 2000 units with Mvt. type 2000 and other cancellations of Goods issue with mvt. type 645(or 643).

What has been done so far:

1. Inbound delivery created for this STO at receiving plant has been deleted for the pending 1000 Units. The Inbound delivery is auto created via Outbound via means of SPED output.

2. Goods Issue has been cancelled in VL09 for the Outbound delivery created at Sending Plant as well. What should be done further:

The only question is how to Cancel the STO and delete it.

Is there a need to create a new Inbound delivery for pending 1000 units for receving Plant and do GR for this 1000 Units? (note Inbound can only be create by repeating output of SPED in Outbound delivery).

I should be able to share the snapshot tomorrow morning , when in office ( if required for PO history tab). Please share your inputs on this query and provide some solution.

Thanks Vishal

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

0 Answers