cancel
Showing results for 
Search instead for 
Did you mean: 

can we re-run job from sm37

Former Member

Hi Friends,

Is there a possibility to re-run a job if it has failed from transaction sm37, without changing its original schedule start time and date.

If I click on the job and then go to job, repeat scheduling, immediate start and save it does that change the jobs original schedule start time and date.

I know we can do it from se38 by inputting the program name and run it in the background but wanted to know if we can do through sme37.

Thanks

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member

Hi,

You can choose the cancel job - go to the Job menu - Click Repeat Schedule (CtrlShiftF1) - you will get few option choose Immediate then click Right button. Your job will start and get the result.

Regards,

Uday Muley

Former Member
0 Kudos

Hi Uday,

Thanks for the reply, but still it hasnt cleared my doubt.

after i select immediate i understand the job would run, but by doing that would it change the schedule time that was actually set.

Thanks

Former Member
0 Kudos

Hi,

No, when you use "Repeat Scheduling", the job keeps the same values (date, etc.) that the first run, even if it was a dynamic date calculation.

Former Member
0 Kudos

Hi,

These are three objects which are used for job scheduling

S_BTCH_ADM

S_BTCH_JOB

S_BTCH_NAM

By maintaining the auth values for S_BATCH_JOB you can save the job for the next run(check all the objects if you need more options)

Rakesh

Edited by: Rakesh Kulkarni on May 13, 2008 6:54 PM