Skip to Content
0
Former Member
May 06, 2008 at 11:54 AM

How to do BDC to update safety time in the MRP View

172 Views

How will we update “Safety time/act.cov” (MARC-SHZET) from S976

Target Days’ supply (REICZ).

The program will join records from S976 version = “A00” and SPMON = current month +1 (default from selection screen) with MARC. The join will be on plant (WERKS) and material (MATNR).

Update the MARC-SHZET field with the value in S976-REICZ.

If REICZ > 99 make the value in MARC-SHZET = 99