PP/DS rrp3 - Order context - Dynamic Pegging

We have a requirement to peg demand to the earliest firm receipt .

Let us say we have two Sales orders

S1- 01/01 and S2-06/01.

We have a production order P1 on 08/01.

Order context shows Pegging between S2- and P1 . Heuristic creates planned order and Order context pegs S1 with new planned orders.

Our requirement is to Peg S1 with P1 (firm receipt) and Peg S2 with new planned order.

Any suggestion would help. TIA