Dear Experts,

I would like to know the difference in the report KSII (Price Variance) and the Cost centre Report S_ALR_87013611.

For one of the cost Centre Group, the results for Actual and plan and so is the variance in both reports are different. Can you tell what could be the reason? Is the price and cost both same here? Or both are different so the reports output bound to be different?

Thanks all in advance. Efforts will be suitably rewarded.

Rg

vk

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Closed

Former Member
0 Kudos

Can you provide additional info please?

Does this Cost Centre group contain Cost Centre(s) with Activities that were used during the month? Did you calculate the Actual Price of these Activities?

Also, when doing the Cost Centre Activity Type planning (KP26), did you input a Capacity?