I fed my SAP with the PIR for the next 18 months. The MRP run created the necessary planned orders, so I have the BOM and the required hours for the resources. With this data, I could get an estimation of cost for each planned order.

My question is: Does SAP counts with an standard report/ tcode that provides the BOM and the required hours in a massive way and also the cost?

I tried COOISPI, but it only delivers BOM